Manor Farm (Monmouthshire)

Llanvapley, Monmouthshire, Gwent

Manor Farm (Monmouthshire) is a 10.5 MW solar farm project in Wales. The applicant or operator on record is 3C Energy/Conergy. It is recorded as operational since June 2016. The determining authority is Monmouthshire, reference DC/2013/00006.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningJan 2013 (completed)
  2. ConsentedOct 2014 (completed)
  3. ConstructionApr 2016 (completed)
  4. OperatingJun 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-09-22.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

10.500 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Manor Farm (Monmouthshire) is a 10.5 MW solar farm project in Wales. The applicant or operator on record is 3C Energy/Conergy. It is recorded as operational since June 2016. The determining authority is Monmouthshire, reference DC/2013/00006.

Site Schematic

SUBSTATION ? ha Β· 10.5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)10.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

Developer3C Energy/Conergy
Owner / operator3C Energy/Conergy
Year consented2014
Construction started2016
Commissioned / target2016
LocationLlanvapley, Monmouthshire, Gwent
RegionWales
Coordinates51.8346363Β°N, 2.9253203Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)270000

πŸ“… Project Timeline

2013-01-07
2014-10-24
2016-04-18
2016-06-23