Land North West Of Maldon Hall, Spital Road, Maldon, Essex, CM9 6D
Maldon Hall is a 40 MW battery storage project in Eastern. The applicant or operator on record is Green Investment Group. Planning permission has been granted as of May 2019 and it is awaiting construction. The determining authority is Maldon, reference 17/01106/FUL.β¦
Consented / Approved
Project stageConsented
PlanningSep 2017 (completed)
ConsentedMay 2019 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Appeal Granted.
Official register: July 2026
Recorded status: Appeal Granted. Source record updated 2021-12-23.
Registered planning capacity; not measured generation.
Maldon Hall is a 40 MW battery storage project in Eastern. The applicant or operator on record is Green Investment Group. Planning permission has been granted as of May 2019 and it is awaiting construction. The determining authority is Maldon, reference 17/01106/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
40.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Green Investment Group
Owner / operator
Green Investment Group
Year consented
2019
Location
Land North West Of Maldon Hall, Spital Road, Maldon, Essex, CM9 6D