Lussa is a 2.4 MW conventional hydro project in Scotland. The applicant or operator on record is Scottish and Southern Energy (SSE). It is recorded as operational since January 1952. The determining authority is Argyll and Bute.…

Operational Β· Since 1952
Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 1952 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2006-04-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.400 MW
Registered Capacity
1952
Commissioned

πŸ“‹ Project Overview

Lussa is a 2.4 MW conventional hydro project in Scotland. The applicant or operator on record is Scottish and Southern Energy (SSE). It is recorded as operational since January 1952. The determining authority is Argyll and Bute.

Site Schematic

UPPER RES. LOWER RES. PENSTOCK TAILRACE GEN. GRID HEAD: ?m Β· POWER: 2.400 MW Β· ? turbines

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.400 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperScottish and Southern Energy (SSE)
Owner / operatorScottish and Southern Energy (SSE)
Commissioned / target1952
LocationLussa, Strathclyde
RegionScotland
Coordinates56.0327744Β°N, 5.7869845Β°W

Additional published register fields

Registered technologySmall Hydro

πŸ“… Project Timeline

1952-01-01