Lumley Water Treatment Works, Wear Crescent, Great Lumley, Chester Le Street, County Durham, DH3 4JT
Lumley Water Treatment Works - Solar Panels is a 1.9 MW solar farm project in North East. The applicant or operator on record is Northumbrian Water Limited. It is recorded as operational since January 2022. The determining authority is County Durham, reference DM/20/03013/CPO.β¦
OperationalΒ· Since 2022
Project stageOperating
PlanningOct 2020 (completed)
ConsentedDec 2020 (completed)
Construction (completed)
OperatingJan 2022 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2022-01-26.
Registered planning capacity; not measured generation.
Lumley Water Treatment Works - Solar Panels is a 1.9 MW solar farm project in North East. The applicant or operator on record is Northumbrian Water Limited. It is recorded as operational since January 2022. The determining authority is County Durham, reference DM/20/03013/CPO.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Northumbrian Water Limited
Owner / operator
Northumbrian Water Limited
Year consented
2020
Commissioned / target
2022
Location
Lumley Water Treatment Works, Wear Crescent, Great Lumley, Chester Le Street, County Durham, DH3 4JT