Land Off West Haddon Road, Guilsborough, Northamptonshire, Northamptonshire
Lowther Farms is a 1.8 MW solar farm project in East Midlands. The applicant or operator on record is Lowther Farms. It is recorded as operational since July 2014. The determining authority is West Northamptonshire, reference DA/2014/0016.β¦
OperationalΒ· Since 2014
Project stageOperating
PlanningJan 2014 (completed)
ConsentedApr 2014 (completed)
ConstructionJun 2014 (completed)
OperatingJul 2014 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-03-25.
Registered planning capacity; not measured generation.
Lowther Farms is a 1.8 MW solar farm project in East Midlands. The applicant or operator on record is Lowther Farms. It is recorded as operational since July 2014. The determining authority is West Northamptonshire, reference DA/2014/0016.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.800 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Lowther Farms
Owner / operator
Lowther Farms
Year consented
2014
Construction started
2014
Commissioned / target
2014
Location
Land Off West Haddon Road, Guilsborough, Northamptonshire, Northamptonshire