πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Lower road, Garsington - Energy Storage System

Lower Road, Garsington, Oxford, Oxfordshire, OX44 9BN

Lower road, Garsington - Energy Storage System is a 100 MW battery storage project in South East. The applicant or operator on record is Net Zero Twenty One Ltd. The planning application was refused. The determining authority is South Oxfordshire, reference P24/S3557/FUL.…

Refused
Project stageRefused
  1. PlanningNov 2024 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2025-10-07.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

100.000 MW
Power Capacity

πŸ“‹ Project Overview

Lower road, Garsington - Energy Storage System is a 100 MW battery storage project in South East. The applicant or operator on record is Net Zero Twenty One Ltd. The planning application was refused. The determining authority is South Oxfordshire, reference P24/S3557/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)100.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNet Zero Twenty One Ltd
Owner / operatorNet Zero Twenty One Ltd
LocationLower Road, Garsington, Oxford, Oxfordshire, OX44 9BN
RegionSouth East
Coordinates51.7118559Β°N, 1.1711868Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-11-15