Lower Farm, Drointon Lane - Solar farm & Battery Energy Storage

Lower Farm Drointon Lane Grindley, Staffordshire, ST18 0LX

Lower Farm, Drointon Lane - Solar farm & Battery Energy Storage is a 30 MW battery storage project in West Midlands. The applicant or operator on record is Innova Renewables. Planning permission has been granted as of January 2025 and it is awaiting construction. The determining …

Consented / Approved
Project stageConsented
  1. PlanningMar 2023 (completed)
  2. ConsentedJan 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Appeal Granted.

Official register: July 2026

Recorded status: Appeal Granted. Source record updated 2026-02-19.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

30.000 MW
Power Capacity

πŸ“‹ Project Overview

Lower Farm, Drointon Lane - Solar farm & Battery Energy Storage is a 30 MW battery storage project in West Midlands. The applicant or operator on record is Innova Renewables. Planning permission has been granted as of January 2025 and it is awaiting construction. The determining authority is Stafford, reference 23/36938/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)30.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperInnova Renewables
Owner / operatorInnova Renewables
Year consented2025
LocationLower Farm Drointon Lane Grindley, Staffordshire, ST18 0LX
RegionWest Midlands
Coordinates52.8397147Β°N, 1.9629779Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID13549

πŸ“… Project Timeline

2023-03-17
2025-01-14