Sub Station, Lower Dunton Road, Basildon, Essex, SS16 6EB
Lower Dunton Road Battery Storage Facility is a 28 MW battery storage project in Eastern. The applicant or operator on record is Eku Energy. It is recorded as operational since August 2025. The determining authority is Thurrock, reference 20/01491/FUL.β¦
OperationalΒ· Since 2025
Project stageOperating
PlanningOct 2020 (completed)
ConsentedFeb 2021 (completed)
Construction (completed)
OperatingAug 2025 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2026-02-13.
Registered planning capacity; not measured generation.
Lower Dunton Road Battery Storage Facility is a 28 MW battery storage project in Eastern. The applicant or operator on record is Eku Energy. It is recorded as operational since August 2025. The determining authority is Thurrock, reference 20/01491/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
28.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Eku Energy
Owner / operator
Eku Energy
Year consented
2021
Commissioned / target
2025
Location
Sub Station, Lower Dunton Road, Basildon, Essex, SS16 6EB