north east of Chelmsford and North of the A12 between Boreham and Hatfield Peverel, Essex, CM3 3AS
Longfield is a battery storage project in Eastern. The applicant or operator on record is Longfield Solar Energy Farm Limited (part of EDF Renwables). Planning permission has been granted as of June 2023 and it is awaiting construction. The determining authority is The Planning Iβ¦
Consented / Approved
Project stageConsented
PlanningFeb 2022 (completed)
ConsentedJun 2023 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2023-06-26.
Registered planning capacity; not measured generation.
Longfield is a battery storage project in Eastern. The applicant or operator on record is Longfield Solar Energy Farm Limited (part of EDF Renwables). Planning permission has been granted as of June 2023 and it is awaiting construction. The determining authority is The Planning Inspectorate - National Infrastructure, reference EN010118.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Battery chemistry
Co-located with RE
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Longfield Solar Energy Farm Limited (part of EDF Renwables)
Owner / operator
Longfield Solar Energy Farm Limited (part of EDF Renwables)
Year consented
2023
Location
north east of Chelmsford and North of the A12 between Boreham and Hatfield Peverel, Essex, CM3 3AS