Long Mountain

Dunloy, Co. Antrim, Co. Antrim

Long Mountain is a 27.6 MW onshore wind project in Northern Ireland. The applicant or operator on record is Energia Renewables. It is recorded as operational since December 2016. The determining authority is Causeway Coast and Glens, reference D/2006/0104/F.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningMar 2006 (completed)
  2. ConsentedJan 2007 (completed)
  3. ConstructionJan 2016 (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2017-01-04.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

27.600 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Long Mountain is a 27.6 MW onshore wind project in Northern Ireland. The applicant or operator on record is Energia Renewables. It is recorded as operational since December 2016. The determining authority is Causeway Coast and Glens, reference D/2006/0104/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)27.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEnergia Renewables
Owner / operatorEnergia Renewables
Year consented2007
Construction started2016
Commissioned / target2016
LocationDunloy, Co. Antrim, Co. Antrim
RegionNorthern Ireland
Coordinates54.984096Β°N, 6.4420049Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2
No. of Turbines12

πŸ“… Project Timeline

2006-03-08
2007-01-05
2016-01-15
2016-12-15