πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Offshore Wind

London Array

Outer Thames Estuary, 20 km off the Kent and Essex coasts

London Array was the world's largest offshore wind farm from 2013 to 2017, and remains one of the most visited offshore wind sites in the world. Located in the outer Thames Estuary, it is visible from the Kent coast and has become an iconic part of the UK's offshore wind story. T…

Operational Β· Since 2013
630 MW
Installed Capacity
175
Turbines
500k
Homes Powered
2,100 GWh
Est. Annual Output
2013
Commissioned

πŸ“‹ Project Overview

London Array was the world's largest offshore wind farm from 2013 to 2017, and remains one of the most visited offshore wind sites in the world. Located in the outer Thames Estuary, it is visible from the Kent coast and has become an iconic part of the UK's offshore wind story. The project's success with 3.6 MW turbines proved the technology and attracted further international investment.

Site Schematic

β—„ SHORE (~20 km) NORTH SEA / ENGLISH CHANNEL Turbine (Siemens SWT-3.6-120) Export cable

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

⚑ Key Facts

β†’ World's largest offshore wind farm from completion in 2013 until 2017
β†’ Visible from the Kent coast on a clear day
β†’ Received the Queen's Award for Enterprise in 2014
β†’ Phase 2 (200+ turbines) was abandoned due to cost and brent spar habitat concerns
β†’ Siemens SWT-3.6-120 turbines were the industry standard of their era
β†’ Joint venture between Ørsted (then DONG Energy), E.ON and UAE's Masdar

πŸ”§ Technical Specifications

Capacity (MW)630 MW
No. of turbines/units175
Turbine / unit modelSiemens SWT-3.6-120
Unit capacity3.6 MW each
Rotor diameter120 m
Hub height87 m
Foundation typeMonopile
Water depth0–25 m
Distance from shore20 km
Site area245 kmΒ²
Annual output2,100 GWh/year
Homes powered500,000 homes

πŸ”Œ Grid Connection & Infrastructure

Grid connection pointCleve Hill substation, Kent
Voltage132 kV
CfD heldNo (merchant / PPA)

🏒 Development & Ownership

DeveloperØrsted / E.ON / Masdar
Owner / operatorØrsted (25%), E.ON (30%), Masdar (20%), CPPIB (25%)
Year consented2010
Construction started2011
Commissioned / target2013
Capex estimate~Β£1.9 billion
LocationOuter Thames Estuary, 20 km off the Kent and Essex coasts
RegionEnglish Channel
Coordinates51.63Β°N, 1.42Β°E

πŸ“… Project Timeline

2001
London Array project first proposed
2010
Marine and planning consents granted
Nov 2011
Construction begins
Jul 2013
Phase 1 (630 MW) fully commissioned
2017
Surpassed by Walney Extension as world's largest

🌿 Environmental & Planning

Phase 2 was abandoned partly due to concerns about impact on Red-throated Diver habitat in the Outer Thames SPA. This established the precedent for ornithological impact being a decisive factor in offshore wind planning.