Offshore Wind

Triton Knoll

Greater Wash region, approximately 33km off the Lincolnshire coast, Offshore

Triton Knoll is a 857 MW offshore wind project in Offshore. The applicant or operator on record is Innogy. It is recorded as operational since January 2022. The determining authority is The Planning Inspectorate - National Infrastructure.…

Operational Β· Since 2022
Project stageOperating
  1. PlanningFeb 2012 (completed)
  2. ConsentedJul 2013 (completed)
  3. ConstructionSep 2018 (completed)
  4. OperatingJan 2022 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2022-03-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

857.000 MW
Registered Capacity
90
Turbines
2022
Commissioned

πŸ“‹ Project Overview

Triton Knoll is a 857 MW offshore wind project in Offshore. The applicant or operator on record is Innogy. It is recorded as operational since January 2022. The determining authority is The Planning Inspectorate - National Infrastructure.

Site Schematic

β—„ SHORE (~? km) NORTH SEA / OFFSHORE Turbine () Export cable

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)857.000 MW
No. of turbines/units90
Unit capacity9.5 MW each

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperInnogy
Owner / operatorInnogy
Year consented2013
Construction started2018
Commissioned / target2022
LocationGreater Wash region, approximately 33km off the Lincolnshire coast, Offshore
RegionOffshore
Coordinates53.2122723Β°N, 0.8616391Β°E

Additional published register fields

Registered technologyWind Offshore
CfD Allocation RoundAR2
Turbine Capacity (MW)9.5
No. of Turbines90
Height of Turbines (m)187

πŸ“… Project Timeline

2012-02-24
2013-07-11
2018-09-10
2022-01-13