Offshore Wind

Hornsea One

120 km off the Yorkshire coast, between Hornsea and Withernsea

Hornsea One was the world's first gigawatt-scale offshore wind farm when it was fully commissioned in 2019. Located in the southern North Sea, its 174 Siemens Gamesa 7 MW turbines stand approximately 190 metres to blade tip. The project transformed the UK's offshore wind ambition…

Operational Β· Since 2019
1,218 MW
Installed Capacity
174
Turbines
1,000k
Homes Powered
4,200 GWh
Est. Annual Output
2019
Commissioned

πŸ“‹ Project Overview

Hornsea One was the world's first gigawatt-scale offshore wind farm when it was fully commissioned in 2019. Located in the southern North Sea, its 174 Siemens Gamesa 7 MW turbines stand approximately 190 metres to blade tip. The project transformed the UK's offshore wind ambitions and proved that gigawatt projects were commercially viable, paving the way for Hornsea Two, Three and the Dogger Bank complex.

Site Schematic

β—„ SHORE (~120 km) NORTH SEA / NORTH SEA Turbine (Siemens Gamesa SG 7.0-154) Export cable

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

⚑ Key Facts

β†’ First offshore wind farm in the world to exceed 1 GW capacity
β†’ Construction used 4 specialist installation vessels over 18 months
β†’ Monopile foundations weigh up to 1,200 tonnes each
β†’ Subsea cables total over 475 km across the site
β†’ Weather window for installation: April–October only
β†’ Sold 50% stake to GIP for Β£4.46bn in 2019

πŸ”§ Technical Specifications

Capacity (MW)1,218 MW
No. of turbines/units174
Turbine / unit modelSiemens Gamesa SG 7.0-154
Unit capacity7 MW each
Rotor diameter154 m
Hub height102 m
Foundation typeMonopile
Water depth23–28 m
Distance from shore120 km
Site area407 kmΒ²
Annual output4,200 GWh/year
Homes powered1,000,000 homes

πŸ”Œ Grid Connection & Infrastructure

Grid connection pointKillingholme, Lincolnshire (onshore substation)
Voltage400 kV National Grid connection
Export cableThree HVAC 220 kV cables, ~120 km
CfD heldYes β€” Allocation Round 1Β£120/MWh (2012 prices)

🏒 Development & Ownership

DeveloperØrsted
Owner / operatorØrsted (50%), Global Infrastructure Partners (50%)
Year consented2014
Construction started2018
Commissioned / target2019
Capex estimate~Β£4.2 billion
Location120 km off the Yorkshire coast, between Hornsea and Withernsea
RegionNorth Sea
Coordinates53.92Β°N, 1.97Β°E

πŸ“… Project Timeline

2014
Development Consent Order granted by Planning Inspectorate
2016
Offshore transmission owner (OFTO) contract awarded
Sep 2018
First monopile installation
Apr 2019
First power exported to grid
Dec 2019
Full commercial operation declared

🌿 Environmental & Planning

Hornsea One went through one of the most detailed EIAs ever conducted for a UK offshore project. The site was selected to minimise impacts on migratory birds, with exclusion zones around key navigation routes. The export cable route was designed to avoid sensitive seabed habitats. Post-construction monitoring shows the site is becoming an artificial reef habitat.