Land at the SWEB Estate, Romney Avenue, Lockleaze, Bristol, Avon, BS7 9ST
Lockleaze Energy Storage is a 15 MW battery storage project in South West. The applicant or operator on record is Aura Power. It is recorded as operational since December 2017. The determining authority is Bristol, City of, reference 17/01147/F.β¦
OperationalΒ· Since 2017
Project stageOperating
PlanningMar 2017 (completed)
Consented (completed)
ConstructionJun 2017 (completed)
OperatingDec 2017 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2019-01-31.
Registered planning capacity; not measured generation.
Lockleaze Energy Storage is a 15 MW battery storage project in South West. The applicant or operator on record is Aura Power. It is recorded as operational since December 2017. The determining authority is Bristol, City of, reference 17/01147/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
15.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Aura Power
Owner / operator
Aura Power
Construction started
2017
Commissioned / target
2017
Location
Land at the SWEB Estate, Romney Avenue, Lockleaze, Bristol, Avon, BS7 9ST