Consented / Approved
Project stageConsented
  1. PlanningFeb 2024 (completed)
  2. ConsentedNov 2024 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-12-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Power Capacity

πŸ“‹ Project Overview

Lochluichart - Energy Storage Facility is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is Intelligent Land Investments Group. Planning permission has been granted as of November 2024 and it is awaiting construction. The determining authority is Highland, reference 23/05905/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperIntelligent Land Investments Group
Owner / operatorIntelligent Land Investments Group
Year consented2024
LocationGrudie Bridge, Lochluichart, Garve, Highland, IV23
RegionScotland
Coordinates57.6843725Β°N, 4.6787461Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-02-02
2024-11-07