πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Liverpool Energy Management Facility

Land To The South Of, Carnegie Road, Liverpool,, Merseyside, L13 7HY

Liverpool Energy Management Facility is a 49.9 MW battery storage project in North West. The applicant or operator on record is Statkraft UK. It is recorded as operational since March 2022. The determining authority is Liverpool, reference 20F/0550.…

Operational Β· Since 2022
Project stageOperating
  1. PlanningFeb 2020 (completed)
  2. ConsentedNov 2020 (completed)
  3. Construction (completed)
  4. OperatingMar 2022 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2022-03-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Power Capacity
2022
Commissioned

πŸ“‹ Project Overview

Liverpool Energy Management Facility is a 49.9 MW battery storage project in North West. The applicant or operator on record is Statkraft UK. It is recorded as operational since March 2022. The determining authority is Liverpool, reference 20F/0550.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperStatkraft UK
Owner / operatorStatkraft UK
Year consented2020
Commissioned / target2022
LocationLand To The South Of, Carnegie Road, Liverpool,, Merseyside, L13 7HY
RegionNorth West
Coordinates53.4199136Β°N, 2.9275915Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2020-02-21
2020-11-10
2022-03-01