Lying To The South Of Little Hale Drove Little Hale Fen, Lincolnshire, NG34 9BG
Little Hale Drove, Little Hale Fen - Battery Storage is a 99 MW battery storage project in East Midlands. The applicant or operator on record is Root-Power (South) Limited. Planning permission has been granted as of March 2025 and it is awaiting construction. The determining authβ¦
Consented / Approved
Project stageConsented
PlanningNov 2024 (completed)
ConsentedMar 2025 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-04-04.
Registered planning capacity; not measured generation.
Little Hale Drove, Little Hale Fen - Battery Storage is a 99 MW battery storage project in East Midlands. The applicant or operator on record is Root-Power (South) Limited. Planning permission has been granted as of March 2025 and it is awaiting construction. The determining authority is North Kesteven, reference 24/1265/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
99.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Root-Power (South) Limited
Owner / operator
Root-Power (South) Limited
Year consented
2025