Under Construction
Project stageUnder construction
  1. PlanningOct 2022 (completed)
  2. ConsentedAug 2023 (completed)
  3. ConstructionSep 2025 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2026-03-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

200.000 MW
Power Capacity

πŸ“‹ Project Overview

Little Beanit Farm, Balsall Common - Battery Storage is a 200 MW battery storage project in West Midlands. The applicant or operator on record is Penso Power (BW ESS). It is recorded as under construction since September 2025. The determining authority is Solihull, reference PL/2022/02308/PPFL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)200.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPenso Power (BW ESS)
Owner / operatorPenso Power (BW ESS)
Year consented2023
Construction started2025
LocationLittle Beanit Farm Waste Lane Balsall Common Solihull, West Midlands, CV7 7GH
RegionWest Midlands
Coordinates52.3861239Β°N, 1.625067Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2022-10-28
2023-08-31
2025-09-01