Linhay Hill Quarry, Settling Pond, Ashburton, Newton Abbot, Devon, TQ13 7ES
Linhay Hill Quarry, Settling Pond - Solar Panel Array is a 0.53 MW solar farm project in South West. The applicant or operator on record is E & JW Glendinning Limited. Planning permission has been granted as of September 2024 and it is awaiting construction. The determining authβ¦
Consented / Approved
Project stageConsented
PlanningJul 2024 (completed)
ConsentedSep 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2024-10-28.
Registered planning capacity; not measured generation.
Linhay Hill Quarry, Settling Pond - Solar Panel Array is a 0.53 MW solar farm project in South West. The applicant or operator on record is E & JW Glendinning Limited. Planning permission has been granted as of September 2024 and it is awaiting construction. The determining authority is Dartford, reference 0288/24.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.530 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
E & JW Glendinning Limited
Owner / operator
E & JW Glendinning Limited
Year consented
2024
Location