Limekiln, Borlum House - Battery Energy Storage System is a 70 MW battery storage project in Scotland. The applicant or operator on record is Boralex. The scheme is currently in the planning system, submitted July 2025. The determining authority is Scottish Government (S36), refe…

In Planning
Project stageIn planning
  1. PlanningJul 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Application Submitted.

Official register: July 2026

Recorded status: Planning Application Submitted. Source record updated 2025-10-13.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

70.000 MW
Power Capacity

πŸ“‹ Project Overview

Limekiln, Borlum House - Battery Energy Storage System is a 70 MW battery storage project in Scotland. The applicant or operator on record is Boralex. The scheme is currently in the planning system, submitted July 2025. The determining authority is Scottish Government (S36), reference ECU00006154.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)70.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBoralex
Owner / operatorBoralex
Location1500m Se/O Borlum House, Reay, Thurso, Highland, KW14 7RE
RegionScotland
Coordinates58.5601921Β°N, 3.7690483Β°W

Additional published register fields

Registered technologyBattery