Solar Farm

Limebury Farm, Horns Cross - Solar Farm

Limebury Farm, Horns Cross,, Devon, EX39 5QG

Limebury Farm, Horns Cross - Solar Farm is a 6.5 MW solar farm project in South West. The applicant or operator on record is Green Switch Capital Limited. It is recorded as under construction since October 2024. The determining authority is Torridge, reference 1/1096/2022/FULM.…

Under Construction
Project stageUnder construction
  1. PlanningOct 2022 (completed)
  2. ConsentedMay 2023 (completed)
  3. ConstructionOct 2024 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2026-02-19.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

6.500 MW
Registered Capacity

πŸ“‹ Project Overview

Limebury Farm, Horns Cross - Solar Farm is a 6.5 MW solar farm project in South West. The applicant or operator on record is Green Switch Capital Limited. It is recorded as under construction since October 2024. The determining authority is Torridge, reference 1/1096/2022/FULM.

Site Schematic

SUBSTATION ? ha Β· 6.5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)6.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGreen Switch Capital Limited
Owner / operatorGreen Switch Capital Limited
Year consented2023
Construction started2024
LocationLimebury Farm, Horns Cross,, Devon, EX39 5QG
RegionSouth West
Coordinates50.9757761Β°N, 4.3312914Β°W

Additional published register fields

Registered technologySolar Photovoltaics
CfD Allocation RoundAR7a
CfD Capacity (MW)5.2
Mounting Type for SolarGround
Solar Site Area (sqm)103000

πŸ“… Project Timeline

2022-10-28
2023-05-10
2024-10-01