Limberlost Solar Farm

Landfill Site Crookham Common, Thatcham, Berkshire, Berkshire, RG19 8DH

Limberlost Solar Farm is a 0.3 MW battery storage project in South East. The applicant or operator on record is Anesco. It is recorded as operational since December 2015. The determining authority is West Berkshire.…

Operational Β· Since 2015
Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. ConstructionNov 2015 (completed)
  4. OperatingDec 2015 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-11-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.300 MW
Power Capacity
2015
Commissioned

πŸ“‹ Project Overview

Limberlost Solar Farm is a 0.3 MW battery storage project in South East. The applicant or operator on record is Anesco. It is recorded as operational since December 2015. The determining authority is West Berkshire.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.300 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAnesco
Owner / operatorAnesco
Construction started2015
Commissioned / target2015
LocationLandfill Site Crookham Common, Thatcham, Berkshire, Berkshire, RG19 8DH
RegionSouth East
Coordinates51.3811126Β°N, 1.2325081Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID5678

πŸ“… Project Timeline

2015-11-11
2015-12-11