Lethen Wind Farm Wind Turbines and Energy Storage is a 10 MW battery storage project in Scotland. The applicant or operator on record is Fred Olsen Renewables Ltd. The planning application was refused. The determining authority is Scottish Government (S36), reference ECU00002216…

Refused
Project stageRefused
  1. PlanningJan 2022 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2024-04-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

10.000 MW
Power Capacity

πŸ“‹ Project Overview

Lethen Wind Farm Wind Turbines and Energy Storage is a 10 MW battery storage project in Scotland. The applicant or operator on record is Fred Olsen Renewables Ltd. The planning application was refused. The determining authority is Scottish Government (S36), reference ECU00002216.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)10.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperFred Olsen Renewables Ltd
Owner / operatorFred Olsen Renewables Ltd
LocationLand 4700M NW Of Gamekeepers Cottage Nairn, Highland, IV12
RegionScotland
Coordinates57.3995173Β°N, 3.7792387Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID8489

πŸ“… Project Timeline

2022-01-21