πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Leadhills Road, Elvanfoot Phase 2 - BESS

190M Northwest Of 3 Leadhills Road Leadhills Road Elvanfoot, Strathclyde, ML12 6TE

Leadhills Road, Elvanfoot Phase 2 - BESS is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is Elvanfoot Energy Storage 2 Limited. The scheme is currently in the planning system, submitted March 2026. The determining authority is South Lanarkshi…

In Planning
Project stageIn planning
  1. PlanningMar 2026 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Application Submitted.

Official register: July 2026

Recorded status: Planning Application Submitted. Source record updated 2026-03-30.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Power Capacity

πŸ“‹ Project Overview

Leadhills Road, Elvanfoot Phase 2 - BESS is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is Elvanfoot Energy Storage 2 Limited. The scheme is currently in the planning system, submitted March 2026. The determining authority is South Lanarkshire, reference P/26/0243.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperElvanfoot Energy Storage 2 Limited
Owner / operatorElvanfoot Energy Storage 2 Limited
Location190M Northwest Of 3 Leadhills Road Leadhills Road Elvanfoot, Strathclyde, ML12 6TE
RegionScotland
Coordinates55.4399553Β°N, 3.6639623Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2026-03-04