Battery Storage

Lathom (Pilkington Technical Centre) Battery Storage

Land To The E/O Lords Cottage, Hall Lane, Lathom, Ormskirk, Lancashire, Lancashire, L40 6JB

Lathom (Pilkington Technical Centre) Battery Storage is a 2 MW battery storage project in North West. The applicant or operator on record is Lightsource BP. It is recorded as operational since April 2019. The determining authority is West Lancashire, reference 2018/0409/FUL.…

Operational Β· Since 2019
Project stageOperating
  1. PlanningApr 2018 (completed)
  2. ConsentedAug 2018 (completed)
  3. ConstructionApr 2019 (completed)
  4. OperatingApr 2019 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2020-08-05.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Power Capacity
2019
Commissioned

πŸ“‹ Project Overview

Lathom (Pilkington Technical Centre) Battery Storage is a 2 MW battery storage project in North West. The applicant or operator on record is Lightsource BP. It is recorded as operational since April 2019. The determining authority is West Lancashire, reference 2018/0409/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLightsource BP
Owner / operatorLightsource BP
Year consented2018
Construction started2019
Commissioned / target2019
LocationLand To The E/O Lords Cottage, Hall Lane, Lathom, Ormskirk, Lancashire, Lancashire, L40 6JB
RegionNorth West
Coordinates53.568838Β°N, 2.8247247Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID6513

πŸ“… Project Timeline

2018-04-17
2018-08-31
2019-04-01
2019-04-16