Lascar Works is a 20 MW battery storage project in North West. The applicant or operator on record is Anesco. It is recorded as operational since June 2019. The determining authority is Bury, reference 62215.β¦
OperationalΒ· Since 2019
Project stageOperating
PlanningNov 2017 (completed)
ConsentedMay 2018 (completed)
ConstructionMar 2019 (completed)
OperatingJun 2019 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2019-07-03.
Registered planning capacity; not measured generation.
Lascar Works is a 20 MW battery storage project in North West. The applicant or operator on record is Anesco. It is recorded as operational since June 2019. The determining authority is Bury, reference 62215.