Lascar Works is a 20 MW battery storage project in North West. The applicant or operator on record is Anesco. It is recorded as operational since June 2019. The determining authority is Bury, reference 62215.…

Operational Β· Since 2019
Project stageOperating
  1. PlanningNov 2017 (completed)
  2. ConsentedMay 2018 (completed)
  3. ConstructionMar 2019 (completed)
  4. OperatingJun 2019 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2019-07-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

20.000 MW
Power Capacity
2019
Commissioned

πŸ“‹ Project Overview

Lascar Works is a 20 MW battery storage project in North West. The applicant or operator on record is Anesco. It is recorded as operational since June 2019. The determining authority is Bury, reference 62215.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)20.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAnesco
Owner / operatorAnesco
Year consented2018
Construction started2019
Commissioned / target2019
LocationLascar Works, Tanpits Road, Bury, BL9 5BY, Lancashire, BL9 5BY
RegionNorth West
Coordinates53.59751Β°N, 2.2950569Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2017-11-30
2018-05-23
2019-03-26
2019-06-26