Land To The West Of Gelscoe House Farm Outbuildings Gelscoe Lane Diseworth, Leicestershire
Langley Priory, Walnut Yard (Phase 2) is a 6.2 MW solar farm project in East Midlands. The applicant or operator on record is Lark Energy. It is recorded as operational since June 2016. The determining authority is North West Leicestershire, reference 14/00408/FULM.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningMay 2014 (completed)
ConsentedOct 2014 (completed)
ConstructionDec 2014 (completed)
OperatingJun 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2018-09-17.
Registered planning capacity; not measured generation.
Langley Priory, Walnut Yard (Phase 2) is a 6.2 MW solar farm project in East Midlands. The applicant or operator on record is Lark Energy. It is recorded as operational since June 2016. The determining authority is North West Leicestershire, reference 14/00408/FULM.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
6.200 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Lark Energy
Owner / operator
Lark Energy
Year consented
2014
Construction started
2014
Commissioned / target
2016
Location
Land To The West Of Gelscoe House Farm Outbuildings Gelscoe Lane Diseworth, Leicestershire