OS Fields 6230 And 7657 Langar Lane, Colston, Bassett, Nottinghamshire
Langar Lane is a 10 MW solar farm project in East Midlands. The applicant or operator on record is Kappa Solar/ OPDE. It is recorded as operational since June 2016. The determining authority is Rushcliffe, reference 14/01594/FUL.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningAug 2014 (completed)
ConsentedDec 2014 (completed)
ConstructionOct 2015 (completed)
OperatingJun 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-12-15.
Registered planning capacity; not measured generation.
Langar Lane is a 10 MW solar farm project in East Midlands. The applicant or operator on record is Kappa Solar/ OPDE. It is recorded as operational since June 2016. The determining authority is Rushcliffe, reference 14/01594/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
10.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Kappa Solar/ OPDE
Owner / operator
Kappa Solar/ OPDE
Year consented
2014
Construction started
2015
Commissioned / target
2016
Location
OS Fields 6230 And 7657 Langar Lane, Colston, Bassett, Nottinghamshire