Lane Side - Energy Storage is a 100 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Net Zero Twenty Three Limited. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is Bradforβ¦
Consented / Approved
Project stageConsented
PlanningOct 2024 (completed)
ConsentedJul 2025 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-08-19.
Registered planning capacity; not measured generation.
Lane Side - Energy Storage is a 100 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Net Zero Twenty Three Limited. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is Bradford, reference 24/04720/MAF.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
100.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Net Zero Twenty Three Limited
Owner / operator
Net Zero Twenty Three Limited
Year consented
2025
Location