Solar Farm

Land to the south of Hill Farm

Land to the south of Hill Farm, Gayton Road, Kislingbury, Northamptonshire

Land to the south of Hill Farm is a 6.8 MW solar farm project in East Midlands. The applicant or operator on record is TGC Renewables. It is recorded as operational since March 2017. The determining authority is West Northamptonshire, reference S/2015/2469/MAF.…

Operational Β· Since 2017
Project stageOperating
  1. PlanningOct 2015 (completed)
  2. ConsentedJan 2016 (completed)
  3. ConstructionDec 2016 (completed)
  4. OperatingMar 2017 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2017-04-20.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

6.800 MW
Registered Capacity
2017
Commissioned

πŸ“‹ Project Overview

Land to the south of Hill Farm is a 6.8 MW solar farm project in East Midlands. The applicant or operator on record is TGC Renewables. It is recorded as operational since March 2017. The determining authority is West Northamptonshire, reference S/2015/2469/MAF.

Site Schematic

SUBSTATION ? ha Β· 6.8 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)6.800 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperTGC Renewables
Owner / operatorTGC Renewables
Year consented2016
Construction started2016
Commissioned / target2017
LocationLand to the south of Hill Farm, Gayton Road, Kislingbury, Northamptonshire
RegionEast Midlands
Coordinates52.2060792Β°N, 0.9772138Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Are they re-applying (Old REPD Ref) 5291
Solar Site Area (sqm)164000

πŸ“… Project Timeline

2015-10-22
2016-01-14
2016-12-12
2017-03-31