Land North of Chiltern Green F, Lawrence End Park North Herts, Chiltern Green, Luton, Bedfordshire, Bedfordshire, LU2 9PN
Land North of Chiltern Greeen is a 5 MW solar farm project in Eastern. The applicant or operator on record is Lightsource Renewable Energy. It is recorded as operational since March 2016. The determining authority is Central Bedfordshire, reference CB/15/01204/FULL.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningMar 2015 (completed)
ConsentedJun 2015 (completed)
ConstructionJan 2016 (completed)
OperatingMar 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-05-20.
Registered planning capacity; not measured generation.
Land North of Chiltern Greeen is a 5 MW solar farm project in Eastern. The applicant or operator on record is Lightsource Renewable Energy. It is recorded as operational since March 2016. The determining authority is Central Bedfordshire, reference CB/15/01204/FULL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Lightsource Renewable Energy
Owner / operator
Lightsource Renewable Energy
Year consented
2015
Construction started
2016
Commissioned / target
2016
Location
Land North of Chiltern Green F, Lawrence End Park North Herts, Chiltern Green, Luton, Bedfordshire, Bedfordshire, LU2 9PN