Soho Leigh upon Mendip, Radstock, Somerset, BA3 5RD
Land at Soho Farm is a 1.5 MW solar farm project in South West. The applicant or operator on record is Mells Park Trust. It is recorded as operational since March 2014. The determining authority is Somerset, reference 2012/2982.β¦
OperationalΒ· Since 2014
Project stageOperating
PlanningJan 2013 (completed)
ConsentedMay 2013 (completed)
ConstructionNov 2013 (completed)
OperatingMar 2014 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2014-03-26.
Registered planning capacity; not measured generation.
Land at Soho Farm is a 1.5 MW solar farm project in South West. The applicant or operator on record is Mells Park Trust. It is recorded as operational since March 2014. The determining authority is Somerset, reference 2012/2982.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.500 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Mells Park Trust
Owner / operator
Mells Park Trust
Year consented
2013
Construction started
2013
Commissioned / target
2014
Location
Soho Leigh upon Mendip, Radstock, Somerset, BA3 5RD