Land To The West Of, Admington, Adjacent To Preston Bushes, Preston on Stour, Stratford-On-Avon, Warwickshire, CV37 8
Land at Radbrook Pastures is a 20.7 MW solar farm project in West Midlands. The applicant or operator on record is TGC Renewables/NESF. The planning permission has expired. The determining authority is Stratford-on-Avon, reference 15/00588/FUL.β¦
Expired
Project stageConsent lapsed
PlanningApr 2015 (completed)
ConsentedAug 2017 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2020-09-03.
Registered planning capacity; not measured generation.
Land at Radbrook Pastures is a 20.7 MW solar farm project in West Midlands. The applicant or operator on record is TGC Renewables/NESF. The planning permission has expired. The determining authority is Stratford-on-Avon, reference 15/00588/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
20.700 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
TGC Renewables/NESF
Owner / operator
TGC Renewables/NESF
Year consented
2017
Location