Land at Mansfield Road is a 3.7 MW solar farm project in East Midlands. The applicant or operator on record is Derbyshire County Council. The planning permission has expired. The determining authority is North East Derbyshire, reference CD4/0615/36.β¦
Expired
Project stageConsent lapsed
PlanningJul 2015 (completed)
ConsentedJan 2016 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2019-07-18.
Registered planning capacity; not measured generation.
Land at Mansfield Road is a 3.7 MW solar farm project in East Midlands. The applicant or operator on record is Derbyshire County Council. The planning permission has expired. The determining authority is North East Derbyshire, reference CD4/0615/36.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
3.700 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Derbyshire County Council
Owner / operator
Derbyshire County Council
Year consented
2016