πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Land at Five Oaks Farm

Land at Five Oaks Farm, Stane Street, Five Oaks, Billingshurst, West Sussex, West Sussex, RH14 9AZ

Land at Five Oaks Farm is a 5 MW solar farm project in South East. The applicant or operator on record is Low Carbon. It is recorded as operational since March 2016. The determining authority is Horsham, reference DC/15/0501.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningMar 2015 (completed)
  2. ConsentedAug 2015 (completed)
  3. ConstructionOct 2015 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-04-28.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Land at Five Oaks Farm is a 5 MW solar farm project in South East. The applicant or operator on record is Low Carbon. It is recorded as operational since March 2016. The determining authority is Horsham, reference DC/15/0501.

Site Schematic

SUBSTATION ? ha Β· 5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLow Carbon
Owner / operatorLow Carbon
Year consented2015
Construction started2015
Commissioned / target2016
LocationLand at Five Oaks Farm, Stane Street, Five Oaks, Billingshurst, West Sussex, West Sussex, RH14 9AZ
RegionSouth East
Coordinates51.0462832Β°N, 0.4341861Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)119700

πŸ“… Project Timeline

2015-03-27
2015-08-19
2015-10-01
2016-03-31