Land at Fell View Farm, Preston Road, Grimsargh, Preston, Lancashire, Lancashire, PR2 5SD
Land at Fell View Farm (Phase 1) is a 4.2 MW solar farm project in North West. The applicant or operator on record is Anesco. It is recorded as operational since March 2016. The determining authority is Preston, reference 06/2015/0218.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningMar 2015 (completed)
ConsentedJul 2015 (completed)
ConstructionJan 2016 (completed)
OperatingMar 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-03-21.
Registered planning capacity; not measured generation.
Land at Fell View Farm (Phase 1) is a 4.2 MW solar farm project in North West. The applicant or operator on record is Anesco. It is recorded as operational since March 2016. The determining authority is Preston, reference 06/2015/0218.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
4.200 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Anesco
Owner / operator
Anesco
Year consented
2015
Construction started
2016
Commissioned / target
2016
Location
Land at Fell View Farm, Preston Road, Grimsargh, Preston, Lancashire, Lancashire, PR2 5SD