πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Land at Carnegie Road

Carnegie Road, Liverpool, Merseyside, Merseyside, L13 7HY

Land at Carnegie Road is a 20 MW battery storage project in North West. The applicant or operator on record is Ørsted. It is recorded as operational since December 2018. The determining authority is Liverpool, reference 16F/2680.…

Operational Β· Since 2018
Project stageOperating
  1. PlanningNov 2016 (completed)
  2. Consented (completed)
  3. ConstructionOct 2018 (completed)
  4. OperatingDec 2018 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2019-01-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

20.000 MW
Power Capacity
2018
Commissioned

πŸ“‹ Project Overview

Land at Carnegie Road is a 20 MW battery storage project in North West. The applicant or operator on record is Ørsted. It is recorded as operational since December 2018. The determining authority is Liverpool, reference 16F/2680.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)20.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperØrsted
Owner / operatorØrsted
Construction started2018
Commissioned / target2018
LocationCarnegie Road, Liverpool, Merseyside, Merseyside, L13 7HY
RegionNorth West
Coordinates53.4199312Β°N, 2.927637Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2016-11-01
2018-10-24
2018-12-24