πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Land Adjacent to Walpole National Grid Substation - Battery Energy Storage

Adj To Walpole National Grid Substation And White House Farm, Frenchs Road, Wisbech, Cambridgeshire, PE14 7JF

Land Adjacent to Walpole National Grid Substation - Battery Energy Storage is a battery storage project in Eastern. The applicant or operator on record is STP Green Limited. Planning permission has been granted as of November 2025 and it is awaiting construction. The determining …

Consented / Approved
Project stageConsented
  1. PlanningAug 2024 (completed)
  2. ConsentedNov 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-12-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

πŸ“‹ Project Overview

Land Adjacent to Walpole National Grid Substation - Battery Energy Storage is a battery storage project in Eastern. The applicant or operator on record is STP Green Limited. Planning permission has been granted as of November 2025 and it is awaiting construction. The determining authority is King's Lynn and West Norfolk, reference 24/01275/FM.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSTP Green Limited
Owner / operatorSTP Green Limited
Year consented2025
LocationAdj To Walpole National Grid Substation And White House Farm, Frenchs Road, Wisbech, Cambridgeshire, PE14 7JF
RegionEastern
Coordinates52.7321129Β°N, 0.1960329Β°E

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-08-29
2025-11-06