πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Lancaster Wastewater Treatment Works

Stodday Lane, Stodday, Lancaster, Lancashire, Lancashire, LA2 0AG

Lancaster Wastewater Treatment Works is a 1.2 MW solar farm project in North West. The applicant or operator on record is United Utilities. It is recorded as operational since April 2016. The determining authority is Lancaster, reference LCC/2016/0065.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningAug 2016 (completed)
  2. ConsentedJan 2017 (completed)
  3. ConstructionMar 2016 (completed)
  4. OperatingApr 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2018-11-19.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.200 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Lancaster Wastewater Treatment Works is a 1.2 MW solar farm project in North West. The applicant or operator on record is United Utilities. It is recorded as operational since April 2016. The determining authority is Lancaster, reference LCC/2016/0065.

Site Schematic

SUBSTATION ? ha Β· 1.2 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)1.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperUnited Utilities
Owner / operatorUnited Utilities
Year consented2017
Construction started2016
Commissioned / target2016
LocationStodday Lane, Stodday, Lancaster, Lancashire, Lancashire, LA2 0AG
RegionNorth West
Coordinates54.0207011Β°N, 2.8172171Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround

πŸ“… Project Timeline

2016-08-12
2017-01-20
2016-03-07
2016-04-07