Land at, Crow Lane, Old Lackenby, Middlesbrough, Cleveland, TS6 8DN
Lackenby is a 49.9 MW battery storage project in North East. The applicant or operator on record is EDF Energy Renewables. The planning permission has expired. The determining authority is Redcar and Cleveland, reference R/2019/0433/FF.β¦
Expired
Project stageConsent lapsed
PlanningJul 2019 (completed)
ConsentedOct 2019 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2020-08-12.
Registered planning capacity; not measured generation.
Lackenby is a 49.9 MW battery storage project in North East. The applicant or operator on record is EDF Energy Renewables. The planning permission has expired. The determining authority is Redcar and Cleveland, reference R/2019/0433/FF.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
EDF Energy Renewables
Owner / operator
EDF Energy Renewables
Year consented
2019
Location
Land at, Crow Lane, Old Lackenby, Middlesbrough, Cleveland, TS6 8DN