OperationalΒ· Since 2016
Project stageOperating
PlanningOct 2015 (completed)
ConsentedJan 2016 (completed)
ConstructionMar 2016 (completed)
OperatingMar 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-05-26.
Registered planning capacity; not measured generation.
Knottingley B is a 2.4 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Envantage Renewables. It is recorded as operational since March 2016. The determining authority is Wakefield, reference 15/02492/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
2.400 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Envantage Renewables
Owner / operator
Envantage Renewables
Year consented
2016
Construction started
2016
Commissioned / target
2016