Knockkippen Wind, Solar & Battery Farm is a 16 MW battery storage project in Scotland. The applicant or operator on record is Falck Renewables / REG Windpower. Planning permission has been granted as of April 2025 and it is awaiting construction. The determining authority is Scot…

Consented / Approved
Project stageConsented
  1. PlanningJun 2022 (completed)
  2. ConsentedApr 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-07-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

16.000 MW
Power Capacity

πŸ“‹ Project Overview

Knockkippen Wind, Solar & Battery Farm is a 16 MW battery storage project in Scotland. The applicant or operator on record is Falck Renewables / REG Windpower. Planning permission has been granted as of April 2025 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004523.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)16.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperFalck Renewables / REG Windpower
Owner / operatorFalck Renewables / REG Windpower
Year consented2025
LocationKnockkippen Moss, East Ayrshire, KA6 7JH
RegionScotland
Coordinates55.3480069Β°N, 4.4673008Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID10468

πŸ“… Project Timeline

2022-06-24