πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Knockkippen Wind, Solar & Battery Farm

Knockkippen Moss, East Ayrshire, KA6 7JH

Knockkippen Wind, Solar & Battery Farm is a 60 MW onshore wind project in Scotland. The applicant or operator on record is Falck Renewables / REG Windpower. Planning permission has been granted as of April 2025 and it is awaiting construction. The determining authority is Scottis…

Consented / Approved
Project stageConsented
  1. PlanningJun 2022 (completed)
  2. ConsentedApr 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-07-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

60.000 MW
Registered Capacity

πŸ“‹ Project Overview

Knockkippen Wind, Solar & Battery Farm is a 60 MW onshore wind project in Scotland. The applicant or operator on record is Falck Renewables / REG Windpower. Planning permission has been granted as of April 2025 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004523.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)60.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperFalck Renewables / REG Windpower
Owner / operatorFalck Renewables / REG Windpower
Year consented2025
LocationKnockkippen Moss, East Ayrshire, KA6 7JH
RegionScotland
Coordinates55.3480069Β°N, 4.4673008Β°W

Additional published register fields

Registered technologyWind Onshore
Storage Co-location REPD Ref ID11675 & 11676
Turbine Capacity (MW)5
No. of Turbines12
Height of Turbines (m)180

πŸ“… Project Timeline

2022-06-24
2025-04-30