πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Kirkton Energy Farm

1800M SW Of Kirkton Cemetery, Melvich, Highland, KW14

Kirkton Energy Farm is a 20 MW battery storage project in Scotland. The applicant or operator on record is Kirkton Wind Farm Limited. The planning application was refused. The determining authority is Scottish Government (S36), reference ECU00003244.…

Refused
Project stageRefused
  1. PlanningNov 2022 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2026-05-08.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

20.000 MW
Power Capacity

πŸ“‹ Project Overview

Kirkton Energy Farm is a 20 MW battery storage project in Scotland. The applicant or operator on record is Kirkton Wind Farm Limited. The planning application was refused. The determining authority is Scottish Government (S36), reference ECU00003244.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)20.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKirkton Wind Farm Limited
Owner / operatorKirkton Wind Farm Limited
Location1800M SW Of Kirkton Cemetery, Melvich, Highland, KW14
RegionScotland
Coordinates58.5889986Β°N, 3.556003Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID9705

πŸ“… Project Timeline

2022-11-09