Ferrybridge Power Station, Kirkhaw Lane, Knottingley, West Yorkshire, WF11 8RB
Kirkhaw Lane - Battery Storage Energy is a 150 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is SSE Enterprise Contracting. It is recorded as operational since March 2026. The determining authority is Wakefield, reference 21/02758/CPL.β¦
OperationalΒ· Since 2026
Project stageOperating
PlanningNov 2021 (completed)
ConsentedJun 2023 (completed)
Construction (completed)
OperatingMar 2026 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2026-03-31.
Registered planning capacity; not measured generation.
Kirkhaw Lane - Battery Storage Energy is a 150 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is SSE Enterprise Contracting. It is recorded as operational since March 2026. The determining authority is Wakefield, reference 21/02758/CPL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
150.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
SSE Enterprise Contracting
Owner / operator
SSE Enterprise Contracting
Year consented
2023
Commissioned / target
2026
Location
Ferrybridge Power Station, Kirkhaw Lane, Knottingley, West Yorkshire, WF11 8RB