The E/O Kintore Substation, Leylodge, Kintore, Inverurie, Aberdeenshire, AB51 0XY
Kintore Substation, Leylodge - Battery Energy Storage is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is XRE Gamma Limited / EDF. Planning permission has been granted as of September 2024 and it is awaiting construction. The determining authoβ¦
Consented / Approved
Project stageConsented
PlanningDec 2023 (completed)
ConsentedSep 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2024-10-15.
Registered planning capacity; not measured generation.
Kintore Substation, Leylodge - Battery Energy Storage is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is XRE Gamma Limited / EDF. Planning permission has been granted as of September 2024 and it is awaiting construction. The determining authority is Aberdeenshire, reference APP/2023/1234.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
XRE Gamma Limited / EDF
Owner / operator
XRE Gamma Limited / EDF
Year consented
2024
Location
The E/O Kintore Substation, Leylodge, Kintore, Inverurie, Aberdeenshire, AB51 0XY