π Project Overview
Kintore Substation, Leylodge - Battery Energy Storage is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is XRE Gamma Limited. The scheme is currently in the planning system, submitted July 2023. The determining authority is Aberdeenshire, reference APP/2023/1234.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 50 MW |
| Battery chemistry | Stand-alone Storage |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | XRE Gamma Limited |
| Owner / operator | XRE Gamma Limited |
| Location | The E/O Kintore Substation, Leylodge, Kintore, Inverurie, Aberdeenshire, AB51 0XY |
| Region | Scotland |
| Coordinates | 57.218627Β°N, 2.3756572Β°W |