Kinmuck Battery Energy Storage

Kinmuck Farm, Ellon, Grampian, AB41 8DB

Kinmuck Battery Energy Storage is a 105 MW battery storage project in Scotland. The applicant or operator on record is Kinmuck Energy Storage Limited / Island Green Power. Planning permission has been granted as of May 2025 and it is awaiting construction. The determining authori…

Consented / Approved
Project stageConsented
  1. PlanningSep 2023 (completed)
  2. ConsentedMay 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-07-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

105.000 MW
Power Capacity

πŸ“‹ Project Overview

Kinmuck Battery Energy Storage is a 105 MW battery storage project in Scotland. The applicant or operator on record is Kinmuck Energy Storage Limited / Island Green Power. Planning permission has been granted as of May 2025 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004907.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)105.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKinmuck Energy Storage Limited / Island Green Power
Owner / operatorKinmuck Energy Storage Limited / Island Green Power
Year consented2025
LocationKinmuck Farm, Ellon, Grampian, AB41 8DB
RegionScotland
Coordinates57.4160196Β°N, 2.007609Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2023-09-13