Project stageOperating
  1. PlanningMay 2022 (completed)
  2. ConsentedDec 2022 (completed)
  3. Construction (completed)
  4. OperatingOct 2022 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2022-05-16.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.160 MW
Registered Capacity
2022
Commissioned

πŸ“‹ Project Overview

Kingsway - Solar Panels is a 0.16 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Solar Options For Schools Limited. It is recorded as operational since October 2022. The determining authority is York, reference 22/00811/SOLAR.

Site Schematic

SUBSTATION ? ha Β· 0.16 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.160 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSolar Options For Schools Limited
Owner / operatorSolar Options For Schools Limited
Year consented2022
Commissioned / target2022
LocationClifton Green Primary School Kingsway, North Yorkshire, YO30 6JA
RegionYorkshire and Humber
Coordinates53.9727328Β°N, 1.0933342Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarRoof

πŸ“… Project Timeline

2022-05-06
2022-12-15
2022-10-11