Solar Farm

Kincraig - Solar Farm and battery storage system

Kincraig Ellon, Grampian, AB41 7RJ

Kincraig - Solar Farm and battery storage system is a 21 MW solar farm project in Scotland. The applicant or operator on record is Renewable Connections Developments Limited. It is recorded as under construction since October 2024. The determining authority is Aberdeenshire, refe…

Under Construction
Project stageUnder construction
  1. PlanningApr 2022 (completed)
  2. ConsentedOct 2022 (completed)
  3. ConstructionOct 2024 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2025-06-17.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

21.000 MW
Registered Capacity

πŸ“‹ Project Overview

Kincraig - Solar Farm and battery storage system is a 21 MW solar farm project in Scotland. The applicant or operator on record is Renewable Connections Developments Limited. It is recorded as under construction since October 2024. The determining authority is Aberdeenshire, reference APP/2022/0838.

Site Schematic

SUBSTATION ? ha Β· 21 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)21.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperRenewable Connections Developments Limited
Owner / operatorRenewable Connections Developments Limited
Year consented2022
Construction started2024
LocationKincraig Ellon, Grampian, AB41 7RJ
RegionScotland
Coordinates57.3126126Β°N, 2.063879Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Storage Co-location REPD Ref ID11177
Mounting Type for SolarGround
Solar Site Area (sqm)360000

πŸ“… Project Timeline

2022-04-14
2022-10-18
2024-10-01